Regulation (EU) 2024/1735 of the European Parliament and of the Council of 13 June 2024 on establishing a framework of measures for strengthening Europe’s net-zero technology manufacturing ecosystem and amending Regulation (EU) 2018/1724 (Text with EEA relevance)

article  16

CELEX:  02024R1735-20240628

Duration of the permit-granting process for net-zero strategic projects
1. The permit-granting process for net-zero strategic projects shall not exceed:
(a) 9 months for the construction or expansion of net-zero strategic projects with a yearly manufacturing capacity of less than 1 GW;
(b) 12 months for the construction or expansion of net-zero strategic projects with a yearly manufacturing capacity of 1 GW or more;
(c) 18 months for all necessary permits to operate a storage site in accordance with Directive 2009/31/EC.
2. For net-zero strategic projects for which a yearly manufacturing capacity is not measured in GW, the permit-granting process shall not exceed 12 months.
3. Where an environmental impact assessment is required pursuant to Directive 2011/92/EU, the step of the assessment referred to in Article 1(2), point (g)(i), of that Directive shall not be included in the duration for the permit-granting process referred to in paragraphs 1 and 2 of this Article.