FantasticSearch

Scroll to: TopResults

Explore European Union Legislation by Asking a Legal Question

assisted-checkbox

filter-instruction-1
positive-filters
negative-filters
act-filter tabs-all

parameters-title

query

assisted-checkbox:

result-title

total 3

Regulation (EU) 2019/941 of the European Parliament and of the Council of 5 June 2019 on risk-preparedness in the electricity sector and repealing Directive 2005/89/EC (Text with EEA relevance.)

article  2

CELEX:  32019R0941

Definitions For the purposes of this Regulation, the following definitions apply:
(1) ‘security of electricity supply’ means the ability of an electricity system to guarantee the supply of electricity to customers with a clearly established level of performance, as determined by the Member States concerned;
(2) ‘transmission system operator’ means transmission system operator as defined in point (35) of Article 2 of Directive (EU) 2019/944;
(3) ‘distribution’ means distribution as defined in point (28) of Article 2 of Directive (EU) 2019/944;
(4) ‘cross-border flow’ means cross-border flow as defined in point (3) of Article 2 of Regulation (EU) 2019/943;
(5) ‘cross zonal capacity’ means the capability of the interconnected system to accommodate energy transfer between bidding zones;
(6) ‘customer’ means customer as defined in point (1) of Article 2 of Directive (EU) 2019/944;
(7) ‘distribution system operator’ means distribution system operator as defined in point (29) of Article 2 of Directive (EU) 2019/944;
(8) ‘generation’ means generation as defined in point (37) of Article 2 of Directive (EU) 2019/944;
Regulation (EU) 2019/941 of the European Parliament and of the Council of 5 June 2019 on risk-preparedness in the electricity sector and repealing Directive 2005/89/EC (Text with EEA relevance.)

article  2

CELEX:  32019R0941

(9) ‘electricity crisis’ means a present or imminent situation in which there is a significant electricity shortage, as determined by the Member States and described in their risk-preparedness plans, or in which it is impossible to supply electricity to customers;
(10) ‘simultaneous electricity crisis’ means an electricity crisis affecting more than one Member State at the same time;
(11) ‘competent authority’ means a national governmental authority or a regulatory authority designated by a Member State in accordance with Article 3;
(12) ‘regulatory authorities’ means regulatory authorities referred to in Article 57(1) of Directive (EU) 2019/944;
(13) ‘crisis coordinator’ means a person, a group of persons, a team composed of the relevant national electricity crisis managers or an institution tasked with acting as a contact point and coordinating the information flow during an electricity crisis;
(14) ‘non-market-based measure’ means any supply- or demand-side measure that deviates from market rules or commercial agreements, the purpose of which is to mitigate an electricity crisis;
(15) ‘producer’ means producer as defined in point (38) of Article 2 of Directive (EU) 2019/944;
Regulation (EU) 2019/941 of the European Parliament and of the Council of 5 June 2019 on risk-preparedness in the electricity sector and repealing Directive 2005/89/EC (Text with EEA relevance.)

article  2

CELEX:  32019R0941

(16) ‘region’ means a group of Member States whose transmission system operators share the same regional coordination centre as referred to in Article 36 of Regulation (EU) 2019/943;
(17) ‘subgroup’ means a group of Member States, within a region, which have the technical ability to provide each other assistance in accordance with Article 15;
(18) ‘early warning’ means a provision of concrete, serious, reliable information indicating that an event may occur which is likely to result in a significant deterioration of the electricity supply situation and is likely to lead to electricity crisis;
(19) ‘transmission’ means transmission as defined in point (34) of Article 2 of Directive (EU) 2019/944;
(20) ‘electricity undertaking’ means electricity undertaking as defined in point (57) of Article 2 of Directive (EU) 2019/944;
(21) ‘capacity allocation’ means the attribution of cross zonal capacity;
(22) ‘energy from renewable sources’ means energy from renewable sources or renewable energy as defined in point (31) of Article 2 of Directive (EU) 2019/944.